| 
 Hi Alan, 
  
It's really good you're looking at Stachiw, which is 
the bible for viewports. I don't mean to be overly critical, this is probably 
just interpretation (just like with the real bible, no?) I looked up page 460, 
and found a rather dire warning that if you're using a flange you need to 
back it up with a bonded acrylic ring. I agree with your option 
#1, but I think options #2 and #3 really have to be combined. Call it option 
2.5, which consists of machining down the flange AND backing it up with a 
bonded ring.  
  
For those without the book, the dire warning is: 
"In an actual application of free-blown hemispheres with flanges, it was 
found that when the heel backup ring was eliminated the magnitude of tensile and 
compressive meridional stresses increased 1000 and 64 percent, respectively, 
although in an attempt to compensate for the expected increase in stress level 
the thickness of the wall was doubled. (Figure 
11.90)."  Figure 11.90 then shows two ways to use a 
flange, labeled "proper" and "improper". The proper one does indeed have a 
thinner flange, but crucially it also has a bonded acrylic support ring 
inside that flange.  
  
My recommendation would be to do just that, rather than 
assume the dome can be backed up with fiberglass instead of bonded 
acrylic. Or else just take the proven K250 approach. On the K250 the flange area 
is machined off entirely, in other words Kittredge went with option #1. But for 
hold-down convenience he added a bonded acrylic ring on the outer surface 
of the dome. The external ring is over and above the structural 
requirements, it's just to give you a handy hold-down on a dome that's already 
strong enough without it.   
  
thanks, 
 Alec    
  
Hi Alec, 
Thanks for your concern. I'm open to any 
cross-examination of what I'm doing. 
The idea of partially elliminating the flange comes 
from Stachiw's book page 460, as one 
of the solutions to the problem of bending stresses 
at the heel. Apparently there are 3 
options. !/ removing the flange. 2/ glueing a 
supporting ring to the heel or 3/ partially 
removing the heel so that the heel curvature & 
hence stresses are lessened. 
I'm intending to partially remove the flange to the 
point where I still have sufficient flange to 
retain the dome & also support the 
heel curvature with  fiberglass & acrylic glue rather than a glued on 
ring. 
If I retain the flange its the easiest way to 
enable me to hold the dome down. I didn't like other ways that 
impede your vision. 
The guy blowing the dome has the Stachiw book & 
we discussed annealing when I put my order in. 
I want to clamp my dome to a thick steel plate 
& test it separate from the sub first. 
Would be sad if it failed, I'd probably say 
something like "BUM" as the rope that suspended it suddenly got 
heavier. 
Alan 
  ----- Original Message -----  
  
  
  Sent: Thursday, February 18, 2010 2:56 
  PM 
  Subject: RE: [PSUBS-MAILIST] Hatch 
  pressure 
  
  
  Hi Alan, 
    
  Uh-oh, problem. Although it sounds entirely reasonable, 
  that isn't a safe hold-down method. It's essential the flange should be 
  machined entirely off because it's the area of maximum stress in a blown 
  dome. You could only really use the proposed method in an ambient 
  boat. I'll let Greg weigh in as the resident expert, but if he misses 
  this post please be sure to contact him proactively. This is a serious safety 
  issue, not a detail.  
    
  I'm no acrylic expert, but be aware there are other 
  details that set a submersible dome quite apart from what your local supplier 
  may be used to fabricating. Like the annealing protocol, for instance, 
  which as I understand it can have drastic consequences. Viewports are 
  an area in which something may look OK but not be OK. 
    
    
  thanks,
  Alec  
  
  
  Thanks Carsten & Alec, thats great 
  information. 
  I'll add a pressure equalizing valve. If I had a 
  manually operated valve it may 
  cause problems If I forgot to open 
  it. 
  I'm not building a K250, the dome on order is 
  being blown 550mm O/D & from 35mm 
  thick acrylic. I've asked them to trim the flange 
  to 15mm wide & 15mm thick & will have 
  a retaining ring holding it down.  
  I was concerned that maybe I'd gone a bit thin to 
  support the upward lifting force of the 
  dome but it calculates out to  about 1 pound 
  for every inch of flange just at below the surface. 
  Thats providing as Carsten said, the barametric 
  pressure isn't higher than outside the sub. 
  Alan 
    
  
    ----- Original Message -----  
    
    
    Sent: Thursday, February 18, 2010 9:24 
    AM 
    Subject: RE: [PSUBS-MAILIST] Hatch 
    pressure 
    
  
    Hi Alan, 
      
    If it's a K-250 you're building, here's your other 
    data point. I just weighed the hatch, and it's 23.5 kg. So it would be 6.5 
    kg buoyant.  
      
    Alec  
      
       
    
    
    Hi thanks people,  
    I was having trouble understanding this. I just put plastic wrap loosly 
    over the top of a glass & submerged it. 
    Some of the wrap bulged up 
    but you could push parts down below the level 
    of the top of the glass. 
    ( This proves you right ) 
    I am going with  a dome hatch, but 
    haven't designed the locking mechanism yet. 
    The dome will be close to  30kg of boyancy 
    before its mounted. 
    Alan 
      
    
      ----- Original Message -----  
      
      
      Sent: Thursday, February 18, 2010 
      6:51 AM 
      Subject: RE: [PSUBS-MAILIST] Hatch 
      pressure 
      
  
      
      First weigh the hatch in air. Then calculate the 
      displacement of the hatch, which is the weight of the water that would 
      fill an equivalent volume. Subtract the displacement from the weight. If 
      you get a negative number, the hatch will tend to "float" as you describe. 
      I doubt very much that would be the case for any conventional elliptical 
      steel hatch. In the case of an acrylic dome hatch like the K-250, I'd 
      recommend doing the math because I'm less sure of the outcome 
      -- those might be slightly buoyant.  
        
      Alec 
      The 
      contents of this e-mail are intended for the named addressee only. It 
      contains information that may be confidential. Unless you are the named 
      addressee or an authorized designee, you may not copy or use it, or 
      disclose it to anyone else. If you received it in error please notify us 
      immediately and then destroy it. 
      
      
      Hi all, 
      I've brought up this subject before, but are 
      tackling it from a differant angle. 
      How much pressure is exerted upward on a 
      hatch at the moment where the 
      submarine 
      just submerges below the water? This is the 
      point of most force before external water 
      pressure helps close it. 
      If you took your submarine, filled it with 
      water & hung it upside down, would this be the 
      same amount of force, or close to 
      it. 
      In wich case if you have a design like Franks 
      flying saucer that angles up to the hatch, 
      you'd have a lot more force acting upward on 
      the hatch than a K250 where the lifting force  
      would be spread more evenly along the 
      hull. 
      Am I thinking right? 
      Alan 
        
     
 |