Re: [PSUBS-MAILIST] Weighing
Gary R. Boucher schrieb:
>
> My thoughts on W&B
>
....
> To measure the vertical position for the CM I first positioned the sub
> on its fulcrum. I then allowed the bow to be lowered several inches to a
> specific resting position on a concrete block. Since I teach physics at my
> university, I "borrowed" some laboratory masses and a strong weight
> hanger. By strategically placing the masses on the stern at a pre-measured
> point I was able to add mass slowly until the bow began to rise from its
> resting position and angle. Using a little trig I calculated the vertical
> center of mass. This is probably not needed by most sub builders who
> utilize very bottom-heavy designs employing dive planes or ballast changes
> to ascend/descend.
....
> Gary Boucher
Gary I did not understand what you excact did.
Can you explain the little "trig" to
meassure and calculate the vertical CM ?
best regards Carsten